Infinite large works: 3 billion in maneuver for Webuild, between exploded costs and commissioners

In the financial package, the government gave a lot of consideration to infrastructure. And if in Italy you say “infrastructure”, you bring into question Webuild, the global construction giant. In the text approved by the …

Infinite large works: 3 billion in maneuver for Webuild, between exploded costs and commissioners

In the financial package, the government gave a lot of consideration to infrastructure. And if in Italy you say “infrastructure”, you bring into question Webuild, the global construction giant. In the text approved by the Council of Ministers, there are over 3 billion additional euros to complete large infrastructures entrusted to Pietro Salini’s group, as well as to consortia and related companies.

Some of these works experience delays, revisions of timetables and cost increases with extraordinary commissioners appointed to supervise everything. The allocations arrive approximately two months after the controversy over the economic requests made by Webuild towards the institutions, which confirmed a short-term cash requirement of approximately 2.1 billion for the continuation of public construction sites.

Third crossing, costs +80% and activation in 2028

The most relevant case is that of the Third Pass, where the difficulties encountered during the excavation of the tunnels on the Apennines required modifications, but not only that. The works began in 2012 and the intervention ended under the supervision of the extraordinary commissioner Calogero Mauceri: according to the timetable published by the Ferrovie dello Stato group, the activation of the new line is currently scheduled for 2028.

The critical issues concern in particular the geological conditions encountered during the excavations, which forced the engineers to find specific technical solutions. However, important sections of the tunnels were completed in 2026, such as the Novi Ligure interconnection and the Polcevera ventilation tunnel, the latter built by Cossi Costruzioni, another company of the Webuild group.

In 2003, the preliminary project was approved for 4.71 billion euros which rose to 4.96 billion three years later. The latest picture published by the Extraordinary Commissioner indicates 8.49 billion: it means that the cost of the Third Crossing alone has increased by 3.77 billion: 80 percent more than the first estimates. But the calculation did not include the Genoa railway hub and the Campasso connection, which were subsequently included in the integrated project. Thus, the overall costs reached 10.6 billion.

The difficulties also have employment implications. In the meeting between the mayor of Novi Ligure, Rocchino Muliere, and the trade unions, around 300 workers were identified as being laid off and between 16 and 18 already fired. In a note, the municipality reports Webuild’s request for “an additional 3 billion euros to complete the work”. Mayor Muliere declared: “It is essential that it be completed as quickly as possible”, announcing a meeting with the presidency of Cociv to obtain an update on construction sites and employment guarantees.

Trento, twenty months of postponement and 34 contractual reserves

The consortium led by Webuild was awarded the contract for the Trento railway ring road in February 2023 for an amount of approximately 934 million euros. The latest updated variant published in the Official Journal of the European Union brought the value to 951.0 million.

The Anac monitoring available through the Silos parliamentary database indicates 26 July 2026 as the date originally scheduled for the completion of the works. Now, the new reported deadline is March 26, 2028: a twenty-month delay.

The same documentation records, with reference to the data available in August 2025, a total of 199 days of suspension of works, 14 contractual modifications and 34 reservations still to be defined. The documented causes of the suspensions include the discovery of war devices and the need for further design checks on the works which could interfere with the behavior of the aquifer, producing the so-called “dam effect”.

The project also affects the contaminated area of ​​Trento Nord, including the former Sloi and former Carbochimica industrial sites. Overall, in addition to the Webuild lot, the whole life cost increased from approximately 1.28 billion in 2024 to 1.433 billion in 2025: an increase of over 151 million. Now, the maneuver bill adds another 500. This work is also under commissionership and, since March 2026, the commissioner functions have been assumed by the CEO of RFI.

Messina-Catania, increased costs and work until the next decade

Webuild builds the two lots of the Giampilieri-Fiumefreddo railway line, on the Messina-Catania line, in a consortium that holds 70 percent. The new line includes numerous tunnels and viaducts, in addition to technological interventions and the adaptation of connections with the existing network.

fiumefreddo giampilieri webuild line

The preliminary project approved by CIPE in 2005 had a cost of 1.97 billion euros. In the 2024 update of the RFI Program Contract the amount reached 2.36 billion, with an increase of approximately 395 million compared to the first forecast, and then rose again to 2.56 billion in 2025, recording a further 199.26 million increase.

The overall growth compared to the 2005 project is therefore 593.96 million, equal to 30.2%. The 2027 budget – which still has to pass parliamentary scrutiny – provides for another 180 million in funding for the work. Completion date expected for 2032.

Salvini: “The contractor asked for more time and money”

Matteo Salvini also said it. At the end of September, the Minister of Infrastructure quantified the resources needed by the end of the year for large construction sites at 8 billion euros: “As a ministry alone, I need 8 billion in cash at the end of the year to pay for the work already done”. The sums would be used to pay for work already carried out, variations and would also serve to cover increases in the prices of materials and energy.

Salvini had also spoken about the Trento ring road, whose latest contract value is, as mentioned, around 951 million euros: “The contractor asked for more time and money, so the process of renegotiating the contract was started”. Already on 20 April 2026, referring to the Third Crossing, the minister had warned that “the risk of construction sites being stopped is unfortunately real” due to the increase in costs.

Webuild’s request and the controversy over the 22 billion extra costs

The allocations come after the story that emerged at the beginning of September, when Il Fatto Quotidiano reported economic requests for 22 billion euros attributable to Webuild. On September 9, the group announced a complaint to Consob, contesting the reconstruction.

In the statement, the company specified that it had not made any “request for extra costs” to the government. Instead, it declared that it had sent formal communications relating to credits for work carried out and certified, recovery of charges already incurred and contractual advances required by law.

Pietro Salini CEO of webuild and Matteo Salvini

According to Webuild, the 22 billion include reserves and variations relating to public contracts, largely already submitted to the technical consultative panels. Approximately 13 billion concern reserves for work already carried out, while the remaining part is an estimate relating to work still to be carried out. The company specifies that this is a contractual comparison and disputes that the figure represents a request for financing addressed directly to the government.

Where does the 3.13 billion of the maneuver for the Webuild shipyards go?

In summary, the most significant financing concerns the Terzo Valico dei Giovi, the new railway line between Genoa and the Po Valley, intended to improve connections between the Ligurian ports, Northern Italy and Europe. The maneuver assigns 2.45 billion euros to the work.

From Italians’ bills, bonuses and business aid: here’s how much more we will pay

Another 500 million are destined for the Trento railway ring road, an infrastructure of approximately 13 kilometers which includes a long tunnel and forms part of the strengthening of the southern access to the Brenner Pass. The construction site is entrusted to the Tridentum consortium, 55% owned by Webuild through its own companies, together with Ghella and Collini Lavori.

The remaining 180 million concern the Giampilieri-Fiumefreddo railway doubling, along the Messina-Catania line. The works on the two lots are entrusted to consortia 70% owned by Webuild. The three works absorb a total of 3.13 billion in appropriations.

The “receipt” for infrastructure (and the funds that are not enough)

Between the financial package – yet to be approved – and the latest infrastructure decree, the government is thus financing infrastructure. The 2027 budget bill provides a total of 8.32 billion multi-year for RFI and Anas: 6.32 billion for maintenance, investments and railway safety, including 3.13 billion for the three works mentioned, and 2 billion for the Anas program contract, distributed between 2028 and 2029.

Bridge over the Strait, what happens if it is not done: how much are the penalties

The Infrastructure Decree then provides 527 million to adapt the A24-A25 tunnels, but using resources already allocated and reprogrammed. The issue remains that of extra costs. Salvini had instead asked for 8 billion by the end of 2026 to pay higher costs for works already carried out.

According to ANCE, compensation for the cost of materials remains to be financed. In the hearing on the measure, the association indicated approximately 1.8 billion in compensation still expected for works carried out in 2025, involving over 13 thousand construction sites, and requested further coverage for 1.4 billion.